01What changes in Hobart
TasNetworks publishes a residential solar connection process for systems under 10 kW on single-phase supply or under 30 kW on multi-phase supply. It says its part of a straightforward connection averages about four to six weeks, while a connection requiring network changes or upgrades can average four to seven months; the retailer then arranges metering and final connection. Those timeframes should shape Hobart advertising.
“Install immediately” is not a safe universal promise. Coverage across Glenorchy, Clarence, Kingborough and Brighton should also follow the installer’s real quote and crew schedule rather than a broad pin around the city.